| Description |
Date(s) |
| Approval--UH Board of Regents |
November 15, 2001 |
| Ground Breaking Ceremony |
April 26, 2002 |
| Libraries "Brown Room" on 5th floor converted to temporary office space for Information Services |
COMPLETED |
| Relocate ITV studio room 14 to Law Trailer Village |
COMPLETED |
| Construct utility trench at southeast side of library |
COMPLETED |
| Relocate Honors College to Law Trailer Village |
COMPLETED
|
| Relocate Houston Teachers Institute on 2 red to Law Trailer Village |
COMPLETED
|
| Demolition of existing southwest library wing |
COMPLETED
|
Construct New Library Wing A basement plus three above ground floors. All new floors will connect into the existing library space. |
COMPLETED (Floors 1-3) Basement December, 2004 |
| Opening of New Library Wing as shared space. Services will be temporary consolidated during the following 10 months |
COMPLETED
|
| Honors College Moves into their completed facility on the 2nd floor. |
COMPLETED
|
| Technical Support Services (TSS) occupies their new addition in the basement. During this period TSS will also experience some renovation to their existing space. |
COMPLETED
|
| Major Renovation of the existing library building. This includes all areas of the first floor and some areas in the basement and the second floor red wing. |
Mid to Late March, 2005--COMPLETED |
| All Departments & Services Move into Completed Building. All four floors of the new wing will open into the existing building to create a state-of-the-art facilty for users. |
Summer, 2005-- COMPLETED
|
| Official Ribbon Cutting Celebration |
February 15, 2006 |
| Install Decorative Light Fixture in 24/hr Lounge |
March, 2006
|
| Renovation of 5 Brown |
March, 2006-- COMPLETED |
| Renovation of 7 Blue & 8 Blue |
May, 2006
|
| Renovation of 1 Brown (mail room area) |
May, 2006
|